Safety stock when the lead time is eight weeks or more

Shop-floor rules of thumb break when goods spend two months at sea. The formula, the inputs and the mistakes to avoid.

3 min read

Container port with cranes at dusk, seen from above

Safety stock is the stock you hold for the demand you did not forecast. With a one-week lead time, small errors barely matter: you can reorder next week. With an eight- or twelve-week lead time from Asia, every error in the forecast is multiplied by the time it takes to correct it.

The standard formula

For demand that varies but a lead time that is reliable:

Safety stock = z × σ × √L

  • σ is the standard deviation of weekly demand, or better, of the weekly forecast error.
  • L is the lead time in weeks.
  • z comes from the service level you want: about 1.28 for 90%, 1.65 for 95%, 2.05 for 98%.

The square root matters. Doubling the lead time does not double safety stock; it multiplies it by about 1.4.

When the lead time itself varies

Sea freight is rarely on time. Port congestion, transshipment and customs add days or weeks. If the lead time varies, use the fuller version:

Safety stock = z × √(L × σ² + d² × σL²)

where d is average weekly demand and σL is the standard deviation of the lead time in weeks. For long, unreliable routes, the second term is often larger than the first: the uncertainty in when goods arrive outweighs the uncertainty in what sells.

Inputs people get wrong

  • Using demand variation instead of forecast error. A seasonal item varies a lot, but if the forecast captures the season, the error is small. Safety stock should cover the error.
  • One service level for everything. 98% on C items ties up cash for little benefit. Set higher levels for A items and lower for C.
  • Forgetting the review period. If you order every two weeks, you are exposed for lead time plus two weeks, not lead time alone.
  • Ignoring open orders. The reorder point compares against stock on hand plus stock on order, not stock on hand alone.

From safety stock to a reorder point

The reorder point is the demand over the lead time plus safety stock. When stock on hand plus stock on order falls below it, it is time to order. The order quantity then covers the next review period, rounded to cartons and the supplier's minimum.

Check it against reality

Once a quarter, look at the items that ran out and the items that sat. If A items still run out, raise their service level or shorten the review period. If C items sit for months, lower theirs.